RFP Documents

Platte River Power Authority – HQ23-1859 - 2023 Request for Proposals (RFP) for Capacity and Associated Energy

Notice of Intent to Bid

Platte River Power Authority – HQ23-1859 – 2023 Request for Proposals (RFP) for Capacity and Associated Energy

Appendix A – Proposal Submittal Form for Capacity and Associated Energy

Platte River Power Authority – HQ23-1859 – 2023 Request for Proposals (RFP) for Capacity and Associated Energy

Platte River RFP Schedule 

Milestone

Deadline

RFP Issued

July 12, 2023

Notice of Intent to Provide Proposal Deadline (5:00 PM MPT)

July 18, 2023

Final Date for RFP Question Submittal

July 26, 2023

Proposal Submission Deadline (8:00 AM MPT)

August 7, 2023

Notification of Results

DELAYED

Execution of Power Supply Agreements (Subject to Negotiation)

As early as September 2023

Bidder/Stakeholder
Questions and Responses

Responses to all relevant questions submitted will be provided below.
Click Here to Ask a Question!

Relevant questions and responses related to the Platte River 2023 RFP for SPP Power Supply Resources will be posted on this page. 

Yes, as long as they are relevant to the RFP.

Responses to questions will be provided as soon as practical. Response times will vary depending upon the complexity of the question.

All questions received prior to August 1, 2023, are currently under review. Responses will be posted soon.

Platte River may deliver to an alternate Delivery Point located within Platte River’s transmission system where there is available transfer capability for the entire term of the Agreement.  Platte River may incur an additional cost to deliver to an alternate Delivery Point, which will be considered when evaluating proposals.

Respondents are encouraged to provide proposals that conform with the guidelines outlined in the RFP and the structure provided in Appendix A. Conforming offers allow Platte River to objectively evaluate all bids and determine which proposal will provide the greatest benefit to Platte River and its customers.

No, Platte River requires notification to take energy deliveries by 7:00 AM (MPT) under the WECC Preschedule Calendar.

Nominations must be made in alignment with the WECC Preschedule Calendar so nomination must be on Friday for the weekend unless the calendar indicates otherwise.

In determining our available capacity, Platte River considers our pre-existing firm commitments and our native load. After taking into account these pre-existing commitments, Platte River is selling only capacity above its planning reserve requirements and will curtail energy deliveries only if it cannot reliably serve native load and pre-existing firm commitments. Platte River will treat this product as a firm commitment from an operational standpoint (for example, applicable NERC standards).

Any forced outage of generating units where Platte River is not able to reliably serve its native load and pre-existing firm commitments.

Platte River will not purchase firm gas for this transaction.  Due to the location of our gas units near the Cheyenne Gas Hub, Platte River typically has natural gas generation available during the winter months.